Data Center Redesign Kickoff

by Angela Miller
On Friday we kicked off the data center project at NCTD, and rarely have I been so excited about the probable success of a project.  Our vendors are Roel Construction (Rob Netzer) and Logicalis (Bob Mobach).  We were lucky to find vendors that have such competency and experience in data center design, and specifically in the requirements for attaining LEED certification.

This is a large undertaking for a small entity like NCTD.  While I can justify the project purely on the long-term anticipated Return-on-Investment, the deal was sweetened by meeting all of the requirements for the Federal Stimulus program.

The overall project has several elements that will hopefully qualify it for LEED certification, including:

  • The anticipated reduction in power demand and increase in power utilization efficiency in the facility
  • The re-use of the building, and materials within the facility for the project (for example, we are supplementing our green fire system instead of replacing it, we’re going to reuse doors instead of purchasing new ones, etc.
  • The ability to reset the ambient temperature of the data center much higher – we expect to set it around 80 degrees instead of the 68 we maintain today
  • The installation of over 220 Kw solar system onsite to more than offset the power draw of the data center
  • The use of in-line cooling instead of the two air handling units currently in the room (these will be recycled for other purposes in the District)

In addition, as I’ve mentioned in previous posts, the District has been committed over the last two years to slowly introducing greener, more sustainable approaches to our information technology infrastructure, including virtualization and consolidation, switching to blade server technology, replacing older equipment with more energy-efficient equipment, and testing desktop virtualization.

All of these steps make solid financial sense for the District – an especially important consideration given the tight financial times we are currently facing.  I could not in good conscience recommend these investments if I could not show solid ROI for our troubles.  While we want to be an agency with a priority on sustainability as part of our mission, it is logical that we could not choose to make these investments if they required a corresponding reduction in service or positions at the District.  Instead, choosing to follow the more sustainable path will realize direct operating cost savings on a monthly basis for the District.

We of course face some challenges to our ambitious timeline.  One of those challenges is the delay of a system migration project by 90 days after its anticipated completion.  This project is attempting to move our Prime System applications (installed in 1986) from a minicomputer to a client-server web interface.  We cannot risk downtime on this environment and therefore out-of-the gate may see a 90-day delay.  But every IT project faces challenges, and I am confident the team will find an approach that gives us what we need.

Over the next several weeks I will be blogging about the adventures of upgrading our data center.  Hopefully in March I will be able to say that we’ve completed the work and that we are on track with our ROI.

Share and Enjoy:
  • Print
  • Digg
  • del.icio.us
  • Facebook
  • Google Bookmarks
  • email
  • LinkedIn
  • PDF
  • Slashdot
  • Technorati
  • Twitter

Leave a Comment

Comment moderation is in use. Please do not submit your comment twice -- it will appear shortly.